Hampton Roads Sanitation District (HRSD) - King William, VA
Project #1- New 0.2 MGD Biological Nutrient Removal (BNR) MBR Facility
![]() |
![]() |
REC was the Prime Engineer on a design build project for Hampton Roads Sanitation District (HRSD) Small Communities Division. Siemens Water Technologies teamed with REC and Mid Eastern Builders to furnish equipment and install a 0.2 MGD MBR package plant in 9 Months that would meet the TN= 3 mg/l and TP = 0.3 mg/l. The project consisted of the following services:
- QC/QA of all process calculations
- BioWIN Modeling
- DEQ Permitting (PAE document)
- Civil, Mechanical, Structural and Electrical Engineering
- Construction Observation and Engineering Services
- Start up and Operations Assistance.